2401 W. Emaus Avenue - Data Center
Description
Amended preliminary/final land development application to revise a previously approved warehouse into a 75-megawatt data center with an electrical substation and sound walls.
Impact summary
If eventually approved, the site would draw up to 75 megawatts — potentially the city's second-largest power consumer — with diesel backup generators near homes and Camelot for Children.
Applicant
- Name
- Quantm Group, LLC
- Address
- 2401 W. Emaus AvenueSee this on the map
At a glance
- Hearings
- 3
- Public comments
- 41
- Total mentions
- 3
Last vote · Planning Commission
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Meeting timeline (3)
Planning Commission — October 13, 2026
Third public meeting on converting a warehouse into a 75-megawatt data center with 32 diesel generators; the applicant offered many voluntary conditions but no vote appears in the available record.
Planning Commission — September 8, 2026
Amended plan to convert a previously approved warehouse into a data center with an electrical substation and sound walls.
Planning Commission — June 9, 2026
Amended land development plan to convert a previously approved 224,000 square foot warehouse into a data center with a 23,342 square foot addition.
Related issues (1)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Allentown
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.