Low PriorityTaxes Budgetopen

Contractor payments and bond release

Summary

Council closed out two Jet Jack water-flow repair contracts and paid Stonemile Group for early salt building work, plus trimmed the J. Poli bond to $2,200 pending stormwater documents.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jul 21, 2026.

Impact analysis

💰Financial impact

Over $104,000 in contract payments plus a bond cut from $71,244.50 to $2,200.

✅Who benefits

Contractors get paid and the borough keeps a small holdback until stormwater plans are verified.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Baldwin

What the council decided, in plain English — one email a week.

Also follow nearby cities