Contractor payments and bond release
Summary
Council closed out two Jet Jack water-flow repair contracts and paid Stonemile Group for early salt building work, plus trimmed the J. Poli bond to $2,200 pending stormwater documents.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 21, 2026.
Impact analysis
Over $104,000 in contract payments plus a bond cut from $71,244.50 to $2,200.
Contractors get paid and the borough keeps a small holdback until stormwater plans are verified.
Mentions & discussions (1)
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Baldwin
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.