Medium PriorityDevelopmentopen

Lower Bucks Government Services Center construction costs

Summary

Former Rep. Andy Warren questioned the $108,831 change order #26 and the mounting number of change orders, plus news reports of deterioration in the current Administration Building. COO Margie McKevitt said a structural engineer will assess windows, brick, and the rotunda, and promised a cumulative change-order total.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jun 3, 2026.

Impact analysis

💰Financial impact

Change orders #24–#26 alone add about $172,643 to the Rycon contract; total change-order costs and repair costs for the existing building are not yet public.

✅Who benefits

Taxpayers get a better-quality finished building if changes are made before walls close, plus a planned approach to repairing the old building.

⚠️Who could be affected

Taxpayers bear the incremental costs, and some speakers question whether change orders are creeping beyond the original scope.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Bucks County, Pennsylvania

What the council decided, in plain English — one email a week.