Caliber Collision site development
Description
Council released $827,030 of the developer's $909,733 bond since most site work is complete; $82,703 stays held until a fire hydrant at the corner intersection is finished.
Impact summary
The project is nearly done and the remaining bond ensures the last piece — the fire hydrant — gets completed.