Baldassari mowing contract overrun

Summary

Council had to approve an extra $39,200 for mowing 70 acres of state hospital grounds because invoices exceeded the not-to-exceed contract — with McMahon questioning how a do-not-exceed agreement was exceeded.

At a glance

Total mentions
1
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Oct 29, 2026.

Impact analysis

💰Financial impact

$39,200, expected to be recouped after the state hospital sale.

✅Who benefits

The contractor and residents of the well-kept hospital grounds area.